Project Overview
- LocationPortland, ME
- OwnerCity of Portland
- EngineerCity of Portland, ME – Public Services Dept., Engineering Section
- CompletedIn progress...
- Contract$658,899
- Services
Scope of Work:
- Install approximately 445LF of 36- to 48″ mainline storm drain pipe
- Support existing gas, electric, water and sewer utilities
- Install manholes, T-bases, catch basins and associated storm drain laterals to mainline storm drain
- Replacement and/or resetting of existing features impacted by construction
- Full depth removal and replacement of road gravels within the pipe trenches
- Full depth removal and replacement of bituminous pavement within the pipe trenches in the vicinity of York Street and High Street intersection, as shown on the plans
- Pavement repairs and pavement overlay as shown on the plans for the paved access/parking area between Becky’s Diner and Gowen Marine
- Reconstruct rock sea wall as necessary to accommodate new 48″ diameter storm drain outfall
- Reconstruct ADA pedestrian ramps and sidewalks at three corners of the York Street and High Street intersection
- Loam, seed and mulch all disturbed areas that are not directed to receive other surface treatment, including a minimum 1FT wide strip on either side of each road within the road reconstruction area